BRISBANE, AUSTRALIAQGC LNG (QUEENSLAND GAS LNG PROJECT) - JUNE 2012 TO MAY 2013
Plant size:
Twenty two (22) field compressor stations
Five (5) central processing Plants
Scope: Installation and plant commissioning
Developing and implementation of DCPs (Dynamic Commissioning Procedures)
Preparation of functional tests, Verification of installation completeness and correctness. Single equipment and system testing. Initial energization of equipment. Investigation of complex system commissioning problems. Repair of identified faults. Execution of Performance Guarantee testing. Preparation of reports, documentation clients operators training and plant hand over to client.
Zero accident